Pune Metro’s Phase-1 Northern Extension from PCMC to Bhakti Shakti Progressing Rapidly 

Maha Metro Gets Green Signal For PCMC-Nigdi Extension

Maha Metro Gets Green Signal For PCMC-Nigdi Extension

Share This News

Pune: The northern extension of Pune Metro’s Phase-1, connecting PCMC (Pimpri-Chinchwad Municipal Corporation) to Bhakti Shakti, is progressing rapidly. Operated by Maharashtra Metro Rail Corporation (MahaMetro), Phase-1 of the Pune Metro was completed in September 2024 and received an overwhelming response from commuters. To further enhance connectivity, MahaMetro has undertaken the extension of Phase-1 at its northern (PCMC) and southern (Swargate) ends.

The proposed elevated northern corridor spans 4.519 km and is advancing with remarkable speed, thanks to the active cooperation from the Pimpri-Chinchwad Municipal Corporation and the traffic police, along with the necessary clearances.

The corridor is expected to alleviate traffic congestion in this industrial and institutional hub, which houses defense establishments, government offices, and several colleges, leading to significant vehicular crowding. The metro promises to reduce commuting challenges and vehicular pollution in the area. Traffic management strategies are currently in place to ensure smooth progress of the metro construction.

Balwadkar

Local citizens and municipal authorities have extended strong support to the metro project. MahaMetro has shared the following official progress updates:

IMG-20250324-WA0012
  • Foundations completed: 28 out of 151
  • Piers erected: 13 out of 151
  • Segments cast: 201 out of 1,337

The northern extension is poised to benefit commuters and contribute to sustainable urban transport in the region.