Mumbai-Pune Missing Link Project Deadline Extended to May 2025

Mumbai-Pune Missing Link Project Deadline Extended to May 2025

Mumbai-Pune Missing Link Project Deadline Extended to May 2025

Share This News

The deadline for the Mumbai-Pune Missing Link Project has been extended to May 2025, despite significant progress. The Maharashtra State Road Development Corporation (MSRDC) is overseeing the project, which aims to reduce travel time and distance between the two cities.

Started in March 2019, the Missing Link Project is about 85% complete. It includes a double tunnel spanning from Khopoli to Koosgaon in Lonavala. Work on the tunnel is nearly finished, while the cable-stayed bridge is in the final stages of construction.

98% of tunnel work is complete, with only internal systems remaining. Two connecting bridges are being constructed, with one 1.8 km bridge finished and the 950-meter cable-stayed bridge 60-65% complete. The project will open to traffic after completion in May 2025.

The 13.3 km-long Missing Link Project features two major tunnels—one 1.67 km and the other 8.92 km long. The project utilizes modern technology for safety. The completed section will include Asia’s widest tunnel (23.30 meters) with four lanes and an emergency lane.

The cable-stayed bridge is 650 meters long, with pillars rising 180 meters and a span of 305 meters between pillars. The project aims to eliminate the steep slopes and ghat sections of the current expressway, making the 19 km stretch from Khopoli to Sinhagad Institute a “zero fatality corridor.”

Sancheti College
Sancheti College