Track doubling work on Pune-Miraj section ; find out details

Pune Pulse Track doubling work on Pune-Miraj section ; find out details

Track doubling work on Pune-Miraj section ; find out details

Share This News

By: Pune Pulse

October 31, 2023

Pune: Central Railways has completed the railway track doubling work at various sections on the Pune-Miraj route.

Balwadkar

As per further information from Central Railways, Adarki-Wathar’s 10.10 km section doubling work was completed & commissioned for traffic on 31/10/23.

IMG-20250324-WA0012

New track safe certification was given by Manoj Arora CRS (Commissioner of Railway Safety) with inspection conducted by Vivek Kumar Gupta, Chief Administrative Officer (construction), Indu Dubey, Divisional Railway Manager /Pune and Suresh Pakhare, Chief Engineer.

The Central Railway has completed 147.77 km multitracking (New line/doubling/3rd/4th line) in the current FY from April 2023 till date.

Rs 3886.95 crores planned by CR this year for new lines/doubling/3rd/4th line/gauge conversion. Rs 2983.47 crores expenditure done till date (76%).

Pune-Miraj doubling project:

Total Length – 279.05 km

Completed doubling – 184.95 km (66.27%)

Total Cost – Rs 4872.53 Crores

Expenditure to date – Rs 3241.06 Crores (66.51%)

Overall physical progress – 86%

Land Acquisition completed – 97.05 Hectares/115 Hectares (84.39%)

Completed sections:

184.95 km (66.27 %)

Pune-Shindawane

Ambale-Wathar

Palsi-Jarandeshwar

Satara-Koregaon

Shenoli-Sangli

Near completion sections (Likely in this Year):

63.60 km (22.79%)

Palsi-Wathar

Satara-Jarandeshwar

Shenoli-Targaon

Sangli-Miraj

In progress:

30.50 km (10.86%)

Ambale-Shindawane

Koregaon-Targaon

Completed works:

Earthwork – 2.87 Crs Cum/3.29 Crs Cum (87%)

Blanketing – 17.48 Lcum/36.5 Lcum (48%)

Major bridges – 57/75 (76%)

Minor bridges/RUB – 373/484 (77%)

ROB – 7/10 (70%)

Tunnels – 2.6/3 numbers

Saphale-Adarki 274 mtr tunnel completed

Adarki-Wathar 169 mtr tunnel completed

Ambale-Shindawane 110 mtr tunnel in progress

Tunnel lengths completed – 475/545 meter (87%)

Station buildings – 29/32 (91%)

Track linking – 240 km/280 km (86%)

Signalling Electronic interlocking – 22/32 stations (69%)

OHE Electrification – 151/280 km (54%)

Completion of this doubling will improve the mobility of trains on the Pune-Miraj busy route & will reduce congestion.