Mumbai-Pune Expressway Missing Link Opening May Be Delayed Amid West Asia Conflict
Mumbai-Pune Expressway Missing Link Opening May Be Delayed Amid West Asia Conflict
Bitumen shortage and rising fuel costs threaten May 1 launch of key Maharashtra infrastructure project
The much-awaited Mumbai-Pune Expressway Missing Link project may not meet its planned May 1 inauguration deadline, as disruptions caused by the ongoing West Asia conflict have begun affecting critical construction supplies.
Officials from the Maharashtra State Road Development Corporation (MSRDC) have indicated that procuring bitumen—an essential material used in road surfacing—has become increasingly difficult over the past two weeks. Prices have reportedly surged by nearly 50%, primarily due to disrupted imports from key supplier countries such as Iraq, Iran, the United Arab Emirates, Saudi Arabia, Oman, and Kuwait.
The shortage has directly impacted the final phase of construction, particularly the surfacing work on the project’s two cable-stayed bridges. While the tunnels and approach roads were completed and layered with bitumen earlier, the bridges were structurally completed only in mid-March, leaving their final surfacing pending.
In addition to bitumen, the supply of light diesel oil—used to operate machinery involved in asphalt and tarring work—has also been affected. This has further slowed down progress on finishing activities.
A section of MSRDC officials has acknowledged that under current circumstances, the inauguration “may have to be postponed.” However, efforts are still underway to adhere to the original timeline. Contractors have reportedly been instructed to complete pending work by April 25, with load testing of the bridges scheduled for April 30.
The 13.3-km Missing Link project is designed to create a faster and safer alternative route between Khopoli and Kusgaon, bypassing the accident-prone and congested ghat section of the existing Mumbai-Pune Expressway. The project includes two tunnels measuring 8.87 km and 1.68 km, along with two cable-stayed bridges of approximately 650 metres each.
First proposed in 1995, the project aims to significantly reduce travel time and improve road safety on one of Maharashtra’s busiest corridors. Construction contracts were awarded in 2018, but progress faced delays due to the COVID-19 pandemic.
As of now, major structural work has been completed, including tunnels and surface roads. Final-stage activities such as installation of lamp posts, painting, and finishing works on the bridges are currently in progress.
Despite the uncertainty, authorities continue to push for completion within the deadline. However, the evolving geopolitical situation and its impact on global supply chains may ultimately determine whether the project opens as scheduled or faces a delay.



